Representing a coal-fired power plant for losses resulting from severe construction damages


King & Spalding represented the owners of an 898 megawatt coal-fired power plant in connection with claims under a construction all risk/delay in start-up policy for losses resulting from severe damage to a boiler during construction of the plant.